BOILER PLANT & STEAM DISTRIBUTION SYSTEM

Location: Alexandria VA Medical Center, Pineville, LA

Scope of work: Federal government project to renovate the existing 8,000 square foot boiler plant and the construct a new 2,087 square foot building addition.

Building 14 will house three new 600 HP fire tube boilers and the addition will include electrical equipment room, control room and personnel facilities, and a new 400kW emergency generator. 

This project will also replace the existing underground portion of the high-pressure steam distribution and pumped condensate return system including replacing four existing fuel oil tank.

Completed: 2024

 

COOLING TOWER REPLACEMENT

Location: Lebanon, PA

Scope of work: Federal Government Design/Build project to design and replace the cooling towers, pumps, and drives at the Center Chiller Plant.

The design includes fully signed and sealed contract drawings and specifications.

Work includes relocating the cooling tower to a new location including piping, valves, controls, and power. Other work includes concrete slabs, utilities, pre-engineered buildings, and new roofs.

Completed:  June 2023

HOFFMAN COURTHOUSE AIR HANDLER REPLACEMENT

Location: Norfolk, VA                                                                 

Scope of work: Federal Government project to demolish and replace six air handlers and associated piping, controls, electrical, equipment, and accessories.

Other scopes of work include asbestos abatement, structural steel, doors, and finishes.

Completed:  August 2022

INSTALL SOFTWATER EQUIPMENT

Location: New Orleans, LA

Scope of work: Federal Government project to furnish and install new softwater equipment and all associated piping and utilities for a fully functioning softwater treatment system.

Due to excessive water hardness produced by the City, a water softener is needed in order to preserve existing equipment and systems at the VA medical center.

The softwater system will be fully integrated into the medical center’s existing domestic water system.

The work includes: removal and relocation of existing utilities, installing new utilities inside and outside the existing Central Energy Plant.

Completed: January 2022

 

 BOILER BURNER REPLACEMENT

Location: Las Vegas VA Medical Center, North Las Vegas, NV

 

Scope of work: Federal government project to replace all the burners, burner controls and associated instrumentation, valves and ancillary equipment on the three existing firetube boilers. Work includes all necessary engineering and design for the new system to tie into the VA’s existing system.

The boilers shall connect to all utility (electrical, piping, valves, starters, control and wiring etc.) connections as necessary for “turn-key” operation.

The boilers support an operational hospital therefore steam supply must be maintained at all times.

Thus the contract requires the the provision for a temporary dual fuel boiler that is equal in capacity to the existing boilers.

Completed:  September 2021

NEW BOILER PLANT

 

Location: Malcom Randolph VA Medical Center, Gainesville, Florida 

Scope of work: Replacement of three aging water tube boilers with three fire tube boilers that provide steam for the whole medical center campus.

A new 6,800 square foot boiler plant building and graphics control station will be constructed.

The current boilers will remain online until the new boiler plant is ready for operations after commissioning.

Once the new boiler plant is placed in service, the current boilers will be demolished and removed.

The boiler plant building includes foundations, concrete, structural steel, roofing, brick envelope, finishes, and all mechanical, electrical, plumbing, fire protection, and specialized systems.

Completed:  July 2021

 

 

 

REPLACE BOILERS 2 & 3

Location: VA Medical Center, Grand Island, Nebraska

Scope of work: Demolition and replacement of the two existing steam boilers including new controls and other system modifications required for the new boiler to function with the existing boiler that will remain.

The new boilers are High Efficiency, and both fuel oil & natural gas capable. Other equipment includes steam meters, water meters, and natural gas meters.

Other construction includes demolition, steel access platforms, framing, insulation, drywall, mechanical, plumbing, electrical, specialty systems, roofing and finish. 

Completed: January 2021

 

 REPLACE BOILERS BUILDING 14

Location: Marion VA Medical Center, Marion, Illinois

 

Scope of work: Remove three existing 300 HP boilers and replace with three new 250 HP boilers in 3000 square foot Building 14 Boiler Plant.

Work also includes removing and installing new deaerators, surge tank, feed water system, pumps and associated mechanical and electrical systems.

Building construction includes demolition and installation of new structural steel and platforms, trenching systems, concrete pads, and exterior windows.

This project requires temporary boilers to provide heat and steam to the campus during construction.

 

Completed: March 2020

REPLACEMENT OF ENERGY PLANT BOILERS

 

Location: C.W. Bill Young VA Medical Center, St. Petersburg, Florida

 

Scope of work: Removing and replacing three boilers, pumps, fans, and all piping for the 8,800 square foot Energy Plant.

Other associated work includes replacing electrical systems and lights and plumbing.

Structural work includes concrete slab and steel demolition, ductile iron piles, reinforced concrete pads, and new steel catwalk system.

 

Completed: March 2020 

BayPines

HOFFMAN COURTHOUSE CHILLER REPLACEMENT

 

18011 Hoffman Courthouse

Location: Walter E. Hoffman Federal Courthouse, Norfolk, VA

 

Scope of work: Federal government project to remove and replace two chillers, six pumps, cooling tower drives, new piping, and associated mechanical equipment.

Project provides 600 tons of cooling for the Hoffman Courthouse. Work also includes replacing the control valves for 24 air handling units.

Other scopes of work are new concrete pads, lead abatement, DDC Controls, and new electrical panels, breakers, and feeders.

Work will be completed in a fully operational and occupied Federal Courthouse.

The use of a temporary chiller will be used to keep building cooling and chilled water in use during construction.

 

Completed: July 2019 

REPLACE CENTRAL BOILER PLANT CONTROLS SYSTEM

Location: Kansas City VA Medical Center, Kansas City, Missouri                                                                                                                                                                                                           

Scope of Work: Installation of equipment, panels, and component parts for a complete replacement and upgrade of the control systems for 4 Central Boiler Plant boilers located in Building 4.

Work also includes programming, upgrades, modifications, testing, and calibration of controls systems. Added work included removing and replacing the deaerator and associated equipment..

Completed: July 2019

MAGNETIC BEARING CHILLER PLANT

Location: St. Petersburg VBA Regional Office, St. Petersburg, FL

Scope of work: Demolish and install a new Modular Chiller Plant, which consists of two 400Ton magnetic bearing compressors and an aesthetically pleasing, external cooling tower. Work includes site preparation, visually appealing barrier walls and all ancillary components such as pumps, motors, piping, valves, electrical and controls. This project supports 700 employees in 212,000 square feet of office space, all in support of providing benefit programs for 1.8 million Veterans.  

Completed: August 2017

Chiller Plant in NC

BOILER PLANT REPLACEMENT

Location:  James E. Van Zandt VA Medical Center, Altoona, PA

Scope of work:  Remove and replace three Boilers, deaerator, feed water pumps, and all piping for steam, feed water, fuel oil and natural gas. 

Other associated work includes electrical and new lights, control air compression, new flooring and finishes, overhead doors, steel catwalk system, and administrative office renovations. 

This project required use of temporary boilers, generator and associated pumps to allow for steam delivery to the Medical Center during construction.

Completed:  August 2017

Altoona Boiler

BUILDING 2 EMERGENCY GENERATOR

Location: Salem VA Medical Center

Scope of work: Asbestos Abatement and demolition of existing building, slab foundation, and emergency generator.

Install new concrete foundations and new 600kW emergency generator to service Building 2.

Tie in generator to existing building systems such as controls, power, and fire alarm. Work includes ensuring temporary generator remains in service during project.

Completed: November 2016

ICU ROOFTOP FANS

Location: Hampton Medical Center, Hampton, VA

Scope of work: Remove and replace four rooftop fans for the Intensive Care Unit (ICU) at Building 110.

Work includes demolition of existing fans, ductwork, and associated supports; power and electrical work; BACnet controls systems; new fans, supports, and ductwork.

Due to the sensitivity of the ICU area, work requires temporary fan use with limited shutdowns to the building area. 

Due to the sensitivity of the ICU area, work requires temporary fan use with limited shutdowns to the building area and close coordination with VAMC Nursing and Doctor staff.

Completed: September 2015

14040 final picture